Case Study

Bleckmann – Phase 2

The Challenge

Having previously installed 16 runs of pallet racking for Bleckmann in phase one, complete with anti-collapse mesh and end of aisle barriers, Bleckmann required additional racking to be installed in their warehouse, returning to Nene for assistance for phase 2.

The Solution

Nene worked with Bleckmann to install a further 16 runs of pallet racking, including anti-collapse mesh and end of aisle barriers. Using the expert installation team from Nene, the installation of the additional racking was planned and undertaken safely and efficiently once again.

The Finished Outcome

Nene completed phase 2 of the racking installation in 4 weeks, installing a total of 32 runs of racking in a total of 8 weeks from start to finish.

Work With Nene

If you think Nene could help with your next warehouse project by offering a full turnkey solution, please contact our team today.